NextEra Energy
Nemaha County, Kansas

Soldier Creek 345kV Substation
Nemaha County, Kansas
Description of Project

Construction of a new 345/34.5kV Substation

Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.

California State University
Fresno, CA

Long Beach, CA
Owner: City of Long Beach
Project Overview

Construction new 12 kV Switchgear Building including switchgear, cable vaults, incoming PG&E, manholes, interrupter switch, 12 kV loop feeder distribution control system and campus power monitoring system.

  • Feeder Loop 1 – Feeds 26 facilities on West side of campus.
  • Feeder Loop 2 – Feeds 17 facilities in the Central/ South sides of the campus.
  • Feeder Loop 3 – Feeds 24 facilities on the North/East sides of the campus.
  • Feeder Loop 4 – Feeds Central Plant and New switchgear building

Building incoming low voltage service feeders, switchboards and power meters. Includes connecting the power meters to the local building IDF for connection to the new campus power monitoring system. Underground PG&E infrastructure between Cedar and Chestnut Avenues located on the North side of Barstow Avenue as part of the PG&E Rule 20 design project to underground the existing overhead 12kV pole line as part of a street widening project to add a bicycle lane in the future.

The design includes equipment pads on grade for transformers and capacitors. Created and implemented traffic and pedestrian control plans. Work was performed with the campus remaining operational and active.

California State University
San Francisco, California

California State University
Electrical Substation Replacement
San Francisco, California
Project Overview

The Project consists of furnishing labor and material necessary to remove the existing 12kV main electrical substation on the campus of San Francisco State University in San Francisco, California, and to replace it with a new 12kV main electrical substation, including, but not limited to, performing all necessary site work at the substation site, including construction of concrete slabs, housekeeping pads, sidewalks, fencing and roof structure, sequencing construction and providing temporary power arrangements to maintain electrical service during construction, coordinating with PG&E for cutover of electric metering and service cables to new substation, replacing sections of 12kV feeder cables, replacing 12kV taped splices with modular separable connectors, providing grounding system additions in electrical manholes and modifying the campus power monitoring system and related systems.

Revelle Electrical Switch
Station Expansion

San Diego, CA
Owner: University of California, San Diego
Project Overview
  • Utility infrastructure improvement for a large operational campus.
  • Approximate Contract Value – $11 million
​Scope of Service
  • Build a structure/facility for major utilities such as a medium voltage (12KV) switch station
  • Install a 23 bay switchgear in the new structure / facility
  • Build a medium voltage underground duct bank
  • Upgrade an existing operational utilities structure
  • Install over 1.5 miles of medium voltage cable through duct bank
  • Work with limited staging area

California State University
San Diego, California

California State University
Revelle Switch Station
San Diego, California
Description of Project

Construction of 12kV Switch Station, at the University of California, San Diego, complete with concrete building, MV switchgear, underground ductbank, MV cables, SCADA system, telecom, mechanical, fire alarm, reclaimed water irrigation system, etc., while maintain a fully-operational campus.

Construction included a new 3,200 square foot Architectural Switch Station located in the middle of the UCSD campus. The new Switch Station was used for power distribution and used as the design for future Switch Stations. Ryan Co. installed new switchgear lineup including PT’s, CPT’s, multiple-phase switches, and a quantity of 15 – 40KAIC Vacuum Breakers, as well as spare spaces for future breakers, new feeder circuits, transferred existing feeders from existing vault to the new switch station. Ryan Co. provided coordination for UCSD regarding schedule for outages to prevent any loss of power around the campus or nearby Veteran’s Affairs Hospital. Project also included rebuilding of existing bays in active switchgears to replace breakers with the new 40KAIC breakers in two other substations on campus. Traffic control and safety measures to ensure the safety of the high volume of student pedestrians and vehicles around 30-foot deep ductbank.

Syncarpha Portfolio: 7.2 MWDC

  • Portfolio represents a total of 7.2 MWDC ground mount at three different locations in Berkshire County, MA
  • Project List for Syncarpha Portfolio
    • Hancock I
    • Hancock II
    • Hancock III
  • Full engineering, procurement and construction
  • 335W Trina modules
  • (82) 60kW SMA Sunny Tripower inverters, (4) 20kW SMA Sunny Tripower inverters
  • Terra Smart racking

ConEdison Development 150MW Portfolio

The ConEdison Development Portfolio represents a combined 150MW at six different locations in the Central Valley of California. Some 1000 acres will have been converted into solar photovoltaic facilities by final commissioning in Q4 of 2016.

As the EPC of record for these projects, The Ryan Company oversees the full engineering and construction of the system including: engineering and construction of the entire system including procurement of electrical equipment, structural supports and preparation of the site, including management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, power cables with the associated collection equipment, and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 34.5-11.5kV substation interconnection.

Project Overview

Project List of ConEd Central Valley PV Portfolio

  • Oro Loma Solar- 27.682MW
  • Ducor Solar 1- 26.188MW
  • Ducor Solar 2- 26.188MW
  • Ducor Solar 3- 19.646MW
  • Ducor Solar 4- 26.188MW
  • Avenal Solar- 21.338MW

Equipment (illustrative):

  • SMA 2200 SunnyCentral “Kodiac” inverter
  • Array Technologies v3 single-axis tracker
  • Trina PD14 305-320W modules

Pier T – Shore to Ship
Power Project

Long Beach, CA
Owner: City of Long Beach
Project Overview
  • Construction of Shore-to Ship Power Project at Pier T, Berths T132-T140
  • Approximate Contract Value – $25 million
Scope of Service

The Work includes, but is not limited to, the following items:

  • Construction of 25 kV switchgear adjacent to existing switchgear at the
  • Main Terminal Substation (“MTS”).
  • Construction of Shore-to-Ship Power (“SSP”) Substations SSP 1, SSP2, SSP3 and SSP4.
  • Construction of Shore to Ship Power Outlets SPO-I, SPO-2, SPO-3, SPO-4, SPO-5, SPO-6, SPO-7, SPO-8, SPO-9, SPO-to, and SPO-ll, including wharf modifications for vaults.
  • Construction of equipment pads.
  • Earthwork, including excavation, bedding, filling, grading and segregate, test, reuse and dispose of excavated soil
  • Installation of crushed miscellaneous base and asphalt concrete pavement.
  • Demolition of existing paving, fencing and bollards.
  • Construction of paving, fencing and bollards, including footings.
  • Construction of duct banks, manholes and pull boxes.
  • Construction of conduit systems, including supports, under the existing
  • Construction of existing slurry and cut-off wall penetrations.
  • Installation of conductors in existing and new duct bank systems.
  • Installation and interconnections of new fiber optic cables for Power Logic
  • Communications between SSP substations, MTS switchgear and
  • Provide training for Power Logic software
  • Acceptance Testing
  • Shore to Ship Power System Commissioning.

Colebrook South 5 MWAC
Wind Turbine System

Connecticut’s First Commercial Wind Farm
Project Overview
  • (2) General Electric 2.85- 103 turbines
  • 5KVA 240/120 Transformer
  • Completed in eight months
Scope of Services
  • Full engineering, procurement, and construction (EPC) of entire system
  • Provided and performed project engineering and design
  • Provided and installed civil and site work
  • Provided and installed erosion, sedimentation control and drainage
  • Provided and installed turbine foundations
  • Provided and installed electrical collection substation