Project Details

Completion Date: 2017

Location: Central Valley, California

Client: ConEdison

The ConEdison Development Portfolio represents a combined 150MW at six different locations in the Central Valley of California. Some 1000 acres will have been converted into solar photovoltaic facilities by final commissioning in Q4 of 2016.

As the EPC of record for these projects, The Ryan Company oversees the full engineering and construction of the system including: engineering and construction of the entire system including procurement of electrical equipment, structural supports and preparation of the site, including management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, power cables with the associated collection equipment, and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 34.5-11.5kV substation interconnection.

Project Overview

Project List of ConEd Central Valley PV Portfolio

  • Oro Loma Solar- 27.682MW
  • Ducor Solar 1- 26.188MW
  • Ducor Solar 2- 26.188MW
  • Ducor Solar 3- 19.646MW
  • Ducor Solar 4- 26.188MW
  • Avenal Solar- 21.338MW

Equipment (illustrative):

  • SMA 2200 SunnyCentral “Kodiac” inverter
  • Array Technologies v3 single-axis tracker
  • Trina PD14 305-320W modules

Related Projects

December 2011
NJ Oak Solar Project: 12.9 MWDC

NJ Oak Solar was constructed on a 101-acre site and connects to Atlantic City Electric’s distribution system. The project involved the removal of the dense...

View Project
August 2011
Avenal Solar Projects: 57.7 MWDC

Comprised of 3 projects: Sun City 25.651MWDC, San Drag- 24.369MWDC and Avenal Park- 7.695 MWDC Project Overview Sharp 128W thin-film frameless modules Emerson 1 MW...

View Project
November 2015
Colebrook South 5 MWAC Wind Turbine System

Project Overview (2) General Electric 2.85- 103 turbines 5KVA 240/120 Transformer Completed in eight months Scope of Services Full engineering, procurement, and construction (EPC) of...