Construction of Shore-to Ship Power Project at Pier T, Berths T132-T140
Approximate Contract Value – $25 million
Scope of Service
The Work includes, but is not limited to, the following items:
Construction of 25 kV switchgear adjacent to existing switchgear at the
Main Terminal Substation (“MTS”).
Construction of Shore-to-Ship Power (“SSP”) Substations SSP 1, SSP2, SSP3 and SSP4.
Construction of Shore to Ship Power Outlets SPO-I, SPO-2, SPO-3, SPO-4, SPO-5, SPO-6, SPO-7, SPO-8, SPO-9, SPO-to, and SPO-ll, including wharf modifications for vaults.
Construction of equipment pads.
Earthwork, including excavation, bedding, filling, grading and segregate, test, reuse and dispose of excavated soil
Installation of crushed miscellaneous base and asphalt concrete pavement.
Demolition of existing paving, fencing and bollards.
Construction of paving, fencing and bollards, including footings.
Construction of duct banks, manholes and pull boxes.
Construction of conduit systems, including supports, under the existing
Construction of existing slurry and cut-off wall penetrations.
Installation of conductors in existing and new duct bank systems.
Installation and interconnections of new fiber optic cables for Power Logic
Communications between SSP substations, MTS switchgear and
Skeleton Creek 345kV Substation Garfield County, Oklahoma
Description of Project
Construction of a new 345/34.5kV Substation
Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
Construction of a new 230/34.5kV Substation
Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
Bellflower 138kV Substation W. Lewisville, Indiana
Description of Project
Construction of a new 138/34.5kV Substation
Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
Fish Springs 345kV Substation & 25MW/100MWh BESS Washoe, Nevada
Description of Project
Construction of a new 345KV Substation and 25MW/100MWh Battery Energy Storage.
Scope included 345/34.5kV Substation, 345kV Gen-tie span, 25MW BESS System with 12 battery container & 8 integrated invertors, initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
Engineering, Procurement and Construction of a 126MWac/168MWdc Solar Project.
Scope includes installation of 415W PV modules, support structures, tracker racking system; DC-AC power conversion equipment; DC and AC equipment , enclosures and protective devices; system control, data acquisition and monitoring system; meteorological equipment; revenue meters; electrical service interconnection; security fences, safety barriers and signage, and all other materials.
White Mesa 345kV Substation Crockett County, Texas
Description of Project
Construction of a new 345/34.5kV Substation
Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
Construction of a new 345/34.5kV Solar Substation and 345kV Gen-Tie Line.
Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
White Hills Wind Substation Mohave County, Arizona
Description of Project
Construction of a new 345/34.5kV Substation and 345kV Switching Station
Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.