Completion Date: September 2013
Location: Tulare Valley, California
Client: Consolidated Edison Development (CED)
White River Solar project is a 25.2MWDC solar photovoltaic, grid connected power generation facility.
Ryan’s responsibilities comprised full engineering, procurement and construction of the entire system including procurement of electrical equipment, preparation of the site involving management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, AC power cables, with the associated collection equipment and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 34.5kV-11.5Kv substation.
Project Overview (2) General Electric 2.85- 103 turbines 5KVA 240/120 Transformer Completed in eight months Scope of Services Full engineering, procurement, and construction (EPC) of...
The ConEdison Development Portfolio represents a combined 150MW at six different locations in the Central Valley of California. Some 1000 acres will have been converted...
Norton Solar is a 3.46 MWDC fixed ground-mount solar project. Located in Norton, Massachusetts. Ryan’s responsibilities comprised full procurement and construction of the entire system...
The quality of our people is the cornerstone of our ability to serve our clients. The Ryan Company, Inc. is comprised of the best and the brightest in the industry. Visit our Careers page and find out more!