Home Projects

Corcoran Solar Project: 25.7 MWDC

See all Projects
Project Details

Completion Date: October 2013

Location: Corcoran, California

Client: Consolidated Edison Development (CED)

The site spans over 115 acres and will produce enough power to serve roughly 16,000 homes annually.

Corcoran Solar Project is a 25.7 MWDC solar photovoltaic, grid connected power generation facility. This project was completed in 8 months.

Ryan’s responsibilities comprised full engineering, procurement and construction of the entire system including procurement of electrical equipment, preparation of the site involving management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, AC power cables, with the associated collection equipment and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 34.5kV-11.5Kv substation.

Project Overview

  • ATI’s ground-mount single-axis tracking support structure on impact-driven steel piers
  • PLA with IBEW
  • Yingli 295W & 300W and Canadian Solar 290W polycrystalline modules
  • Emerson 1.06MW inverters
  • All power sold to Southern California Edison (SCE)
  • Quanta Subsidiaries involved:
    • Intermountain Electric, Inc.
    • Dashiell Corporation

Related Projects

2017
ConEdison Development 150MW Portfolio

The ConEdison Development Portfolio represents a combined 150MW at six different locations in the Central Valley of California. Some 1000 acres will have been converted...

View Project
September 2014
Norton Solar 3.46 MWDC Solar Project

Norton Solar is a 3.46 MWDC fixed ground-mount solar project. Located in Norton, Massachusetts. Ryan’s responsibilities comprised full procurement and construction of the entire system...

View Project
January 2013
Alpaugh & Alpaugh North: 92.6 MWDC

Project Overview ATI’s ground-mount single-axis tracking support structure on impact-driven steel piers Completed in 9 months Trina 280W, 285W, & 290W; and Canadian Solar 280W...

View Project
Copyright © 2024 © 2021 The Ryan Company, Inc. All Rights Reserved.