Completion Date: October 2013
Location: Corcoran, California
Client: Consolidated Edison Development (CED)
Corcoran Solar Project is a 25.7 MWDC solar photovoltaic, grid connected power generation facility. This project was completed in 8 months.
Ryan’s responsibilities comprised full engineering, procurement and construction of the entire system including procurement of electrical equipment, preparation of the site involving management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, AC power cables, with the associated collection equipment and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 34.5kV-11.5Kv substation.
The ConEdison Development Portfolio represents a combined 150MW at six different locations in the Central Valley of California. Some 1000 acres will have been converted...
Norton Solar is a 3.46 MWDC fixed ground-mount solar project. Located in Norton, Massachusetts. Ryan’s responsibilities comprised full procurement and construction of the entire system...
Project Overview ATI’s ground-mount single-axis tracking support structure on impact-driven steel piers Completed in 9 months Trina 280W, 285W, & 290W; and Canadian Solar 280W...