Home Projects

Avenal Solar Projects: 57.7 MWDC

See all Projects
Project Details

Completion Date: August 2011

Location: Kings County, California

Client: Eurus Energy Holdings and NRG Solar

Comprised of 3 projects: Sun City 25.651MWDC, San Drag- 24.369MWDC and Avenal Park- 7.695 MWDC

Project Overview
  • Sharp 128W thin-film frameless modules
  • Emerson 1 MW inverters
  • Completed in 10 months
  • Fixed ground-mount support structure on impact-driven steel piers
  • Constructed concurrently for Eurus Energy Holdings and NRG Solar
  • All power sold to Pacific Gas & Electric
  • Quanta Subsidiaries involved:
    • Dashiell Corporation
    • PAR Electric Company
Scope of Services
  • Full engineering, procurement, and construction (EPC) of entire system
  • Preparation of site – management of all project grading, trenching and fencing
  • Installation of the support structures and module racking system
  • Installation of the modules, inverters, DC wiring, AC power cables and the associated collection equipment
  • Procurement of all equipment
  • Design and optimization of project processes and installation
  • Design and installation of the 34.5kV substation

Related Projects

2017
ConEdison Development 150MW Portfolio

The ConEdison Development Portfolio represents a combined 150MW at six different locations in the Central Valley of California. Some 1000 acres will have been converted...

View Project
September 2014
Norton Solar 3.46 MWDC Solar Project

Norton Solar is a 3.46 MWDC fixed ground-mount solar project. Located in Norton, Massachusetts. Ryan’s responsibilities comprised full procurement and construction of the entire system...

View Project
January 2013
Alpaugh & Alpaugh North: 92.6 MWDC

Project Overview ATI’s ground-mount single-axis tracking support structure on impact-driven steel piers Completed in 9 months Trina 280W, 285W, & 290W; and Canadian Solar 280W...

View Project
Copyright © 2024 © 2021 The Ryan Company, Inc. All Rights Reserved.
Back to Top