NJ Oak Solar was constructed on a 101-acre site and connects to Atlantic City Electric’s distribution system. The project involved the removal of the dense brush and trees on site. At the time of completion, the project was the largest non-utility owned project east of the Mississippi and produced enough power to support 8,250 homes.
Ryan’s responsibilities comprised full engineering, procurement and construction of the entire system including procurement of electrical equipment, preparation of the site involving management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, power cables, with the associated collection equipment and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 12.47kV switchyard.
Project Overview
Yingli 235W polycrystalline modules
Satcon 1 MW inverters
Completed in 8 months: April 2011 to December 2011
Fixed ground-mount support structure on impact-driven steel piers
Significant challenges included a hurricane, an early snowstorm and a 5.8 magnitude earthquake
Kern County Water Agency, Bakersfield, CA Contract # KCWA-2007-08
Project Overview
Construction of the Kern County Water Agency
Improvements to District No. 4 Henry C. Garnett Water Purification Plant Service Entrance
Approximate Contract Value – $13.5 million
Scope of Service
Ryan was the prime contractor and electrical contractor
Preparation of site – site clearing, dust control, environmental protection, and perimeter fence
Construction of a new 115kV to 4160v substation and service entrance building
Installation of a 4.16 kV electrical power distribution system comprised of remotely operated medium voltage switchgear
2000kw Stand-by diesel engine generators
Installation of an automatic transfer control system
Providing all electrical raceways, including concrete encased underground ductbanks, cable tray and conduit, and conductors required to connect the following existing facilities
Construction new 12 kV Switchgear Building including switchgear, cable vaults, incoming PG&E, manholes, interrupter switch, 12 kV loop feeder distribution control system and campus power monitoring system.
Feeder Loop 1 – Feeds 26 facilities on West side of campus.
Feeder Loop 2 – Feeds 17 facilities in the Central/ South sides of the campus.
Feeder Loop 3 – Feeds 24 facilities on the North/East sides of the campus.
Feeder Loop 4 – Feeds Central Plant and New switchgear building
Building incoming low voltage service feeders, switchboards and power meters. Includes connecting the power meters to the local building IDF for connection to the new campus power monitoring system. Underground PG&E infrastructure between Cedar and Chestnut Avenues located on the North side of Barstow Avenue as part of the PG&E Rule 20 design project to underground the existing overhead 12kV pole line as part of a street widening project to add a bicycle lane in the future.
The design includes equipment pads on grade for transformers and capacitors. Created and implemented traffic and pedestrian control plans. Work was performed with the campus remaining operational and active.