Campus Crescent Infrastructure Upgrade
Project Overview
  • Mechanical and Electrical Infrastructure upgrades for the complete campus
  • New hot water system to various buildings
  • Completion of the underground 15kV loop throughout the campus including medium voltage switchgear and transformers
  • Ryan was the prime contractor and electrical contractor
  • Preparation of site – performed all project grading, trenching and access roads
  • Furnished and installed all mechanical and electrical infrastructure upgrades
  • Installation of underground medium voltage loop, switchgear and transformers

Related Projects

2024
Shore Power Installation
San Diego, California

Shore Power Installation at NCMT Berths 24-10 and 11 at the National City Marine Terminal. Scope includes demolition, excavation, backfill, debris removal, installation of substation,...

View Project
August 2022
Sun Mountain 230kV Substation
Pueblo, Colorado

Construction of a new 230/34.5kV Substation Scope included initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV...

View Project
September 2016
California State University
Fresno, CA

Project Overview Construction new 12 kV Switchgear Building including switchgear, cable vaults, incoming PG&E, manholes, interrupter switch, 12 kV loop feeder distribution control system and...